First article inspection report with suppliers from China
What belongs in a first article inspection report?
| Component | Content |
|---|---|
| Cover sheet | Part number, drawing revision, supplier, reason for sampling, result |
| Dimensional report | Every dimension on the drawing with nominal, tolerance and actual value per sample |
| Material | Material evidence, e.g. inspection certificate to EN 10204 |
| Function | Results of agreed functional or assembly tests |
| Surface | Coating thickness, adhesion, appearance as agreed |
| Deviations | Clearly marked, with the customer’s concession |
In the automotive industry, sampling follows VDA Volume 2 (PPF) or the AIAG PPAP process. Which documents you actually require is set by your own specifications.
First-article sampling with a factory in China, step by step
- Define the inspection scope. Which characteristics, how many samples, which report format (your form, VDA or PPAP).
- Drawing with characteristic numbers. Number the dimensions on the drawing (“ballooning”) so that report and drawing match unambiguously.
- Samples from the series process. With series tooling, series material and series parameters – no hand-made samples.
- Measurement and report by the supplier, ideally cross-checked by an independent team on site.
- Shipping the samples together with the report; samples clearly labelled.
- Your incoming inspection of selected characteristics.
- Approval, conditional approval or rejection – in writing. Only then does the series start.
Typical mistakes – and how to avoid them
- The report only says “OK” instead of measured values. Require actual values per sample and characteristic.
- Samples from a different process than the series. Write “samples from series tooling and series process” into the order.
- Wrong drawing revision. Compare the drawing index on the cover sheet and the order.
- General tolerances missing. Without a reference (e.g. ISO 2768-m) it is unclear what is being measured against.
- Language misunderstandings. Number the characteristics and define terms bilingually (German/English).
Frequently asked questions
How many first-article samples are usual? The customer decides. Guidelines of large manufacturers often specify several samples per cavity; agree on the number explicitly.
What is the difference between EMPB, ISIR and FAIR? In essence they mean the same thing: documented proof that the first series parts meet the requirements. The terms come from different industries and language areas.
Does every dimension have to be measured? For a full sampling, usually yes. For re-sampling after changes a reduced scope can be agreed.
Who pays for the first articles? That is a matter of negotiation. Clarify the costs for samples, measurement and any re-sampling in the quote.
First articles with a complete measurement report are part of every series project at Schutawill. Request a project
Further reading: VDA Volume 2 “Quality assurance of supplies” (VDA QMC); sampling guidelines of large German manufacturers.
Your drawing.
Our quote.
Upload STEP or PDF – you receive feasibility, process, tooling cost, unit price and lead time.
Upload a drawing- Quote with DFM notes – non-binding
- NDA before the first exchange
- First articles with measurement report